Re-roof of house or block of flats
- Stage 1: commencement, may be combined with stage 2 - minimum two days notice.
- Stage 2: inspect roof timbers after removal of original covering - minimum one day notice.
- Stage 3: check insulation upgraded, felt underlay provided, finish of tiles/slates, provision of flashings.
- Stage 4: completion - minimum one day notice and may be combined with stage 3 if all OK.