Building Control inspection schedule

You must ask us to inspect works at the relevant stages for your building project. This guide lists the stages of inspection for different type of project.

Domestic electrical wiring

This is not done by a part P registered electrician. Relevant to, for example:

  • new electrical circuits
  • consumer unit
  • work in a special location such as near a bath or shower

Stages

  • Stage 1: commencement, may be combined with stage 2 - minimum two days notice.
  • Stage 2: pre-plaster first fix of wiring - minimum two days notice.
  • Stage 3: completion - minimum two day notice.