Building Control inspection schedule

You must ask us to inspect works at the relevant stages for your building project. This guide lists the stages of inspection for different type of project.

Alterations to extend or create a basement

  • Stage 1: commencement, may be combined with stage 2 - minimum two days notice.
  • Stage 2: inspection of new underpins foundations to sequence - minimum one day notice.
  • Stage 3: inspection of oversite, may combine with stage 4.
  • Stage 4: inspection of damp-proof membrane for new floor.
  • Stage 5: inspection of any new walls DPC and foul and surface affected drains.
  • Stage 6: inspection of structural works.
  • Stage 7: inspect drainage connections, if any, above ground including witness of drain tests.
  • Stage 8: completion - minimum one day notice and combined with stage 8 if all OK. Includes fire safety measures of:
    • means of escape provisions in the event of fire
    • ventilation
    • installer certificates, for example as electrical and gas